On-Screen Takeoff: How Estimators Use OST on Commercial Bids

On-Screen Takeoff (OST) is ConstructConnect’s takeoff software for measuring lengths, areas and counts on digital plans. Estimators set and verify the scale, build a condition for each item they price, draw takeoff by bid area, use typical takeoff and overlays to save time, and send quantities to Quick Bid or Excel for pricing. Most of its speed comes from setup, not from drawing faster.

This guide works through how commercial estimators set up a bid in OST, how conditions and the four condition styles work, typical areas, groups and repeating pages, overlay for revisions, linking to Quick Bid or Excel, speed tips, and a short comparison with PlanSwift and Bluebeam Revu.

Key Takeaways
  • On-Screen Takeoff is owned by ConstructConnect and measures lengths, areas and counts; pricing is quote-based, with a 14-day free trial.
  • Conditions come in four styles: linear, area, count and attachment. Properties such as height and thickness let one condition return more than one result.
  • Set bid areas before you draw. Each piece of takeoff belongs to one bid area, and you can use up to three tiers.
  • Typical areas, typical groups and repeating pages let you measure a repeated floor or room once. In the worked example, the estimator draws 2,220 of 4,700 LF.
  • Overlay shows additions in blue and deletions in red: “red is dead, and blue is new.”

Part of our construction estimating software guide, which compares the tools contractors use for takeoff, pricing and bid tracking.

What Is On-Screen Takeoff, and Who Uses It?

On-Screen Takeoff is ConstructConnect’s takeoff product. ConstructConnect says it digitally measures lengths, areas and counts, and lists these tools on its product page:

  • Multi-Condition Takeoff: select several conditions and draw them together to complete a room.
  • Styles: save conditions by trade or discipline so you can reuse them on the next bid.
  • Typical Areas, Groups and Repeating Pages: measure repeated work once.
  • Overlay: compare drawings to spot changes.
  • Quick Bid link: connect takeoff to Quick Bid and other estimating tools.
  • AI tools: Takeoff Boost, which identifies wall types and creates conditions, and an Auto Count that uses bitmap scanning to count objects, annotations and callouts.

Pricing is quote-based and depends on licensing options, and ConstructConnect offers a 14-day free trial. OST is common on commercial bids with many floors, many rooms and frequent addenda, where conditions, bid areas and typical takeoff pay off. For how it fits among other tools, see our comparison of construction takeoff software by trade.

How to Set Up a Bid in On-Screen Takeoff

Setup decides how clean your quantities are on bid day. Work through it in this order:

3D ninja estimator at a monitor showing a floor plan sheet ready for on-screen takeoff, with a stack of drawing sheets on the desk.
Set up the bid and verify scale before the first takeoff.
  1. Create the bid and add plansName the bid the way your estimating system and cost codes expect, then add the plan pages and name each one by sheet number.
  2. Set and verify the scaleConstructConnect’s help center says it is vital to set or calculate and verify scale before drawing takeoff, and recommends against changing a page’s scale after takeoff is drawn. If a sheet has no scale or the stated scale is wrong, calculate it from an object of known length.
  3. Build bid areasBid areas are defined locations within a project, such as buildings, floors, wings, phases or zones. Set them up first: each takeoff object belongs to one bid area, a single piece of takeoff can’t be split between two, and you can add up to three tiers.
  4. Create conditionsAdd a condition for each item you will price, with its style, name and properties. Conditions are organized by layers and types rather than by area.
  5. Load your stylesReuse saved condition sets for your trade so every bid starts from the same names and properties.
Name Conditions by Cost Code

Put the CSI section or your cost code at the front of each condition name, such as 09 21 16 for gypsum board assemblies. Quantities then sort the same way in OST, Excel and your estimate. Our guide to construction cost codes shows how to build that list.

Conditions: Area, Linear, Count and Attachment

A condition is the item you are measuring and the rules for how OST reports it. ConstructConnect lists four basic condition styles:

Style Measures Typical commercial uses Useful properties
Linear Length Partitions, base, curbs, piping and conduit runs Height, to report wall area as well as length
Area Surface Slabs, flooring, ceilings, roofing Thickness, which lets an area condition calculate volume
Count Each Doors, fixtures, devices, footings Name and type for clean grouping
Attachment Adjusts a parent condition Items that modify a parent condition’s results Linked to the parent condition

ConstructConnect’s help center puts it simply: provide the right properties, such as height or thickness, and the program can deliver the results you need. The example below shows how one drawn line or area can carry several quantities.

Condition (example) Style and properties Drawn Results
Partition type A, typical floor Linear, height 10 ft 1,240 LF 1,240 LF; 12,400 SF per side; 24,800 SF both sides
Slab on grade, level 1 Area, thickness 4 in. 6,000 SF 6,000 SF; 2,000 CF; 74.07 CY
Doors, typical floor Count 42 EA 42 EA per typical floor

Example only: 1,240 × 10 = 12,400 SF per side; 6,000 × (4 ÷ 12) = 2,000 CF, and 2,000 ÷ 27 = 74.07 CY before waste. If you bid interiors, our guide to drywall estimating shows how those wall areas turn into board, studs and labor.

For Commercial Estimating Teams

Bids Stacking Up Faster Than Your OST Seats Can Clear Them?

Get Ninja places a dedicated estimator who already works in On-Screen Takeoff on your team, starting within 3 business days.

Book a Discovery Call →

Built for contractors. No spam. No pressure. Just straight answers.

Drawing Area, Linear and Count Takeoff

With conditions built, drawing is the fast part. These habits keep it accurate:

  • Select the bid area first: every object you draw is assigned to one area, so confirm the active area before you start a floor.
  • Draw rooms with Multi-Condition Takeoff: select the floor, base and ceiling conditions together and trace the room once.
  • Trace walls along one consistent line: pick centerline or face for each wall type and stick to it across the bid.
  • Count with review: use Auto Count where your license includes it, then spot-check a sample of sheets and the legend.
  • Check results as you go: group the Takeoff tab by area to see exactly where each quantity comes from.

If you are weighing automated takeoff, our guide to AI takeoff software covers what it does well and what still needs review.

Typical Areas, Typical Groups and Repeating Pages

ConstructConnect calls typical takeoff a time-saving feature of OST: measure one instance of a repeated element and let the software multiply it. There are three methods, and they solve different problems.

Method Best for What you see Watch out for
Typical Areas Repeated areas where only final quantities by bid area matter Totals multiplied by the number of times the area repeats in each bid area Not advised if the job will be managed in Digital Production Control
Typical Groups A defined set of takeoff, such as a hotel room or toilet room, placed in many locations The actual takeoff at each marker you place Works with Digital Production Control
Typical or Repeating Pages Identical floors in a multistory building Virtual pages, one per floor, carrying the typical page’s takeoff Gives breakdowns by area or page

One rule to remember: ConstructConnect notes that Typical Areas and Typical Groups or Repeating Pages cannot be used in the same bid. Pick the method before you start drawing.

Example: a four-story office where level 1 has a lobby layout and levels 2 to 4 are identical. The estimator draws level 1 (980 LF of partitions) and the typical page once (1,240 LF), and OST carries the typical takeoff to levels 3 and 4. Total partitions are 980 + 3 × 1,240 = 4,700 LF, of which 2,220 LF, or 47.2%, is drawn by hand. Doors follow the same pattern: 30 on level 1 plus 3 × 42 = 156.

Example: partition takeoff by level with repeating pagesBar chart for a worked example of a four-story office. Level 1 has 980 linear feet drawn and level 2, the typical page, has 1,240 linear feet drawn. Levels 3 and 4 each carry 1,240 linear feet generated from the typical page, for a total of 4,700 linear feet. Example: partition LF by level with repeating pages Total 4,700 LF; the estimator draws 2,220 LF 980 LF Level 1 1,240 LF Level 2 (typical) 1,240 LF Level 3 1,240 LF Level 4 Drawn by the estimator Generated from the typical page
Example only: quantities from this article’s worked four-story office example.

Using Overlay to Catch Revisions and Addenda

Overlay places a revised drawing over the base drawing so you can see what changed. OST shows overlays in grayscale, marks additions (only on the overlay) in blue and deletions (only on the base) in red. ConstructConnect’s memory aid is “red is dead, and blue is new.”

3D ninja estimator pointing at a monitor where two versions of a floor plan are overlaid, with removed walls in red and new walls in blue.
Overlay shows what changed between drawing revisions.
  1. Add the overlayFrom the Image tab or the Overlay toolbar, pick the revised plan. OST tries to resize it to match the base image automatically.
  2. Resize, align and deskewUse Resize Overlay, Align Overlay and Deskew Overlay until the two sheets line up; scanned revisions often need deskewing.
  3. Toggle and reviewSwitch between base, overlay and both, and review every red and blue area at a normal zoom level.
  4. Revise the takeoff on the base imageDraw changes on the base, not the overlay, and log each change for your addendum summary.
  • Trying to stack several addenda on one page: each base page takes one overlay, so duplicate the base page for each addendum.
  • Using an indexed multi-page PDF as the overlay: overlays must be single-page files.
  • Adding overlays from the Cover Sheet, which changes the image file and can shift takeoff on other pages that use it.
  • Reading pixel noise at high zoom as real changes.

Linking OST to Quick Bid or Excel

OST measures; pricing happens in Quick Bid, Excel or another estimating system. ConstructConnect describes two main routes:

Route How it works Good to know
Quick Bid Export the takeoff bid to create a project in Quick Bid, or link the bid to work interactively with Quick Bid Estimating One person can work in OST and another in Quick Bid, but not at the same time
Microsoft Excel Each condition’s result links to a specific cell or named range in your workbook Refresh with F9 or Bid > Refresh Worksheet; Summary and Estimate tab data can be copied and pasted

The Excel link is a refresh, not a live sync, so refresh before you print a bid summary. A pricing template with named ranges for each condition makes every new bid a fill-in rather than a rebuild.

Tips for Faster On-Screen Takeoff on Commercial Bids

  • Build styles by trade: one saved set of conditions per scope you bid, with CSI-based names.
  • Decide bid areas at kickoff: match them to how the GC’s bid form or schedule of values breaks out the work.
  • Choose your typical method early: repeating pages for identical floors, typical groups for repeated rooms.
  • Verify scale on every sheet: measure a known dimension before drawing, especially on enlarged plans and details.
  • Overlay every addendum: duplicate the base page, overlay the revision and log changes the same day.
  • Link once, refresh often: keep an Excel or Quick Bid template so pricing updates with each refresh.
  • Review by area before pricing: group the Takeoff tab by area and compare against the previous bid of the same building type.

On-Screen Takeoff vs PlanSwift vs Bluebeam Revu

Tool Approach Pricing as listed, October 2026
On-Screen Takeoff Conditions, bid areas, typical takeoff and overlay, with links to Quick Bid and Excel Quote-based; 14-day free trial
PlanSwift Point-and-click takeoff with material, labor and waste assemblies that build the estimate as you measure; sends to Excel or an estimating system Essential $2,000 and Core $3,000 a year for one seat
Bluebeam Revu PDF markup with measurement; count, volume and overlay in Core; Quantity Link with Excel in Complete Basics $260, Core $330, Complete $440, Max $590 per user a year

In short, OST suits estimators who live in conditions and multi-floor commercial sets, PlanSwift suits those who want assemblies to build pricing as they measure, and Revu suits teams whose takeoff sits alongside heavy markup and document review. For a deeper look at the other two, read PlanSwift vs Bluebeam.

How a Dedicated Estimator From Get Ninja Works in On-Screen Takeoff

Get Ninja places a dedicated remote construction estimator on your team, trained in US estimating standards and matched to the trades you bid. Your estimator works in your OST license with your styles and templates.

  • Setup to your standards: bid areas, condition names and styles that match your cost codes and bid forms.
  • Typical takeoff and overlays: repeating pages on multistory work and an addendum log for every revision.
  • Priced output: quantities linked to your Quick Bid or Excel templates, ready for your review.
  • Speed and low risk: Estimators start within 3 business days, with a 3 to 5 day turnaround on a standard estimate, one flat monthly rate, a 30-day money-back guarantee and free replacement for the life of your account.
On-Screen Takeoff

Need Someone Who Already Knows OST to Cover Your Bids?

Get Ninja places a dedicated estimator on your team who works in your software and your templates, starting within 3 business days.

Book a Discovery Call →

Built for contractors. No spam. No pressure. Just straight answers.

Frequently Asked Questions

What is On-Screen Takeoff used for?

On-Screen Takeoff is used to measure lengths, areas and counts on digital plans so estimators can price them. Commercial estimators use its conditions, bid areas, typical takeoff and overlay tools, then send quantities to Quick Bid or Excel.

Who owns On-Screen Takeoff?

On-Screen Takeoff is a ConstructConnect product. ConstructConnect also makes Quick Bid, which OST can export to or link with for pricing.

How do you set the scale in On-Screen Takeoff?

You can set scale from the Cover Sheet, the Takeoff tab settings, the Annotation and View window or the Set Scale dialog. If a drawing has no scale or a wrong one, calculate it from an object of known length, and verify scale before you draw any takeoff.

What is the difference between Typical Areas and Typical Groups in OST?

Typical Areas multiply totals by the number of times an area repeats in each bid area. Typical Groups show the actual takeoff at each marker you place and work with Digital Production Control. The two methods can’t be used in the same bid.

Can On-Screen Takeoff export to Excel?

Yes. Each condition’s result can be linked to a specific cell or named range in an Excel workbook, and you refresh the link with F9 or Bid, Refresh Worksheet. Summary and Estimate tab data can also be copied and pasted into Excel.

How much does On-Screen Takeoff cost?

ConstructConnect does not publish OST prices. Pricing is quote-based and depends on licensing options and business needs, and a 14-day free trial is available.

Sources
  1. ConstructConnect, On-Screen Takeoff. constructconnect.com
  2. ConstructConnect Help, On-Screen Takeoff: starting a new condition (condition styles and properties). help.constructconnect.com
  3. ConstructConnect Help, On-Screen Takeoff 06.01.01: Setting Page Scale Manually. help.constructconnect.com
  4. ConstructConnect Help, On-Screen Takeoff: How to Use Bid Areas to Separate Takeoff Quantities. help.constructconnect.com
  5. ConstructConnect Help, On-Screen Takeoff 10.01: Use Typical Takeoff. help.constructconnect.com
  6. ConstructConnect Help, On-Screen Takeoff 11.07: Using Overlay to Identify Changes Between Revisions. help.constructconnect.com
  7. ConstructConnect Help, On-Screen Takeoff 14.02: Price a Bid Using Microsoft Excel. help.constructconnect.com
  8. ConstructConnect Help, Which Takeoff and Estimating Package Is Right for Your Company. help.constructconnect.com
  9. PlanSwift, Pricing. planswift.com
  10. Bluebeam, Pricing and plan comparison. bluebeam.com

Example quantities are calculated from the stated dimensions. Unit costs, production rates and waste factors are placeholders, not market prices or industry benchmarks. Get Ninja start times are typical, not guaranteed, and pricing is quoted per account.