Olivia Bennet writes Get Ninja's construction estimating guides for US general contractors, home builders and trade contractors: takeoffs, bid preparation, trade pricing and how to staff an estimating backlog. Every article is reviewed by Get Ninja co-founder MJ Suben, who ran a commercial general contracting firm for more than 15 years.
MJ Suben is the co-founder of Get Ninja, which places fully trained, dedicated construction estimators with US general contractors, home builders and trade contractors. Before Get Ninja he ran a commercial general contracting firm for more than 15 years, so he reviews every Get Ninja guide against how real bids are priced, leveled and won.
Construction cost codes are the numbered categories a contractor uses to budget and track job costs, and they work best when every estimate line carries the same code as the budget line it becomes. A CSI-based list pairs a MasterFormat division and section with a cost type: labor, material, equipment, subcontract or other. Get that match right and the estimate, the budget and the cost report all speak the same language.
This guide covers why estimate lines and job cost codes must match, how to build a cost code structure on MasterFormat, how cost types work, a sample code list, how codes feed job costing and change orders, and how to roll the list out in your accounting and project management software.
- Use one format everywhere: division-section plus cost type, such as 03 30 00-L for cast-in-place concrete labor.
- Keep cost types out of the code itself. Labor, material, equipment, subcontract and other are a separate field.
- Short lists win. Sage’s guidance: about a dozen codes for most single-trade subs, and one code per subcontracted trade for a GC.
- In the example, splitting by cost type shows that labor drives 78% of a projected $5,523 overrun on one code.
- Plan the list before the first transaction posts. Changing codes after that is a complex process.
Part of our construction estimating guide, which walks through every stage of an estimate from plans to bid day.
What Are Construction Cost Codes?
A cost code is a category of work that you budget and track on every job. Sage’s help for Sage 100 Contractor describes cost codes as the way to separate costs into categories and compare budgeted cost to actual cost for a job, with divisions grouping codes for subtotals on reports. It also notes that cost codes are company-specific, not job-specific: one list serves every project.
Different systems use different words for the same pieces, which is where most confusion starts:
| Term | What it means | Example |
|---|---|---|
| Cost code | The work the cost is for | 09 29 00 Gypsum Board |
| Cost type | The kind of cost | L labor, M material, E equipment, S subcontract, O other |
| Division | A group of codes for subtotals | Division 09 Finishes |
| Phase or sub job | A job-specific split, such as a building or phase | Building B, Phase 2 |
| Budget code | Procore’s term for the full combination of segments | Cost code plus cost type, plus sub job if used |
Procore notes that some integrated ERP systems use a different term for its cost type concept, so check the vocabulary before you map one system to another.
Why Estimate Lines and Job Cost Codes Must Match
An estimate is a prediction. Job costing is the test of that prediction. If the two use different structures, someone has to translate between them on every job, and the lessons never make it back to the next bid.
- The budget loads itself: the awarded estimate becomes the job budget line for line, with no re-keying.
- Variances point to a cause: a labor overrun on 03 30 00 tells the estimator something a “concrete over budget” note never will.
- Unit costs come back: closeout cost per CY, per SF or per labor-hour feeds the next estimate.
- Change orders price faster: the same codes and rates used in the bid price the change.
- Pay apps line up: a schedule of values built from the same lines makes billing and cost reports easy to reconcile.
How to Build a CSI-Based Cost Code Structure
MasterFormat gives you a ready-made backbone that your specs, estimates and subcontracts already use. Sage’s help adds an important caveat: the CSI system classifies materials and workmanship, not cost breakdowns, and in most cases the first two levels of CSI are enough for cost codes. For how the numbering works, see our guide to CSI MasterFormat for estimators.
- Pick the levelCode at the division and Level 2 section, such as 03 30 00 Cast-in-Place Concrete or 09 29 00 Gypsum Board. Go deeper only for work you self-perform and want to track closely.
- Set one formatDivision-section, a separator, then cost type: 03 30 00-L, 03 30 00-M, 09 29 00-S. Procore’s cost code segment is tiered, with tiers separated by a dash, so a consistent separator imports cleanly.
- Keep cost types separateSage’s guidance is blunt: because every job cost gets a cost type, there is no need for codes that split materials, labor, equipment and subcontracts.
- Size the list to how you workA GC usually needs one code per subcontracted trade unless it self-performs the work. Most single-trade subs need about a dozen codes; Sage puts mechanical subs at around twenty.
- Give allowances their own codesIf the contract has an allowance, track it separately so you can report spending against it and adjust the prime contract by change order for the over or under.
- Add non-CSI codesMasterFormat has no section for fee, bond, insurance or contingency, and you may want time-related general conditions on their own code too. Procore’s default list adds a Division 17 with codes for contingency, insurance, bond and profit, a pattern worth copying.
- Leave room to growUnused section numbers give you space to add codes later without renumbering.
Sage gives a drywall subcontractor example that splits Division 09 by activity: 9250 Stocking, 9255 Hanging, 9260 Taping, 9265 Spraying, 9270 Knockdown and 9275 Cleanup. That detail is for the sub’s own production tracking. GCs and owners rarely need it.
Cost Types: Labor, Material, Equipment, Subcontract and Other
Cost types sort the money inside each code. Sage 100 Contractor presets five (1 Material, 2 Labor, 3 Equipment, 4 Subcontract, 5 Other) and lets you define four more. Procore’s defaults are Equipment, Labor, Materials, Other, Owner Cost, Commitments (S, short for subcontract) and Professional Services.
| Cost type | What goes in it | Where the actual cost comes from |
|---|---|---|
| L Labor | Your own field labor, at a burdened rate | Timecards coded by cost code |
| M Material | Materials you buy and install | Supplier invoices and purchase orders |
| E Equipment | Rented or owned equipment, fuel | Rental invoices and internal equipment rates |
| S Subcontract | Work bought from subcontractors | Subcontracts and their pay applications |
| O Other | Permits, fees, testing, small items | Invoices and receipts |
Price labor in the estimate at the same burdened rate accounting will post. If the estimate uses a bare wage and payroll posts a burdened one, every labor code will look over budget. Our guide to calculating construction labor burden and the free labor burden calculator help you set that rate.
Estimates That Never Line Up With Your Job Cost Reports?
Get Ninja places a dedicated estimator on your team who builds every estimate on your cost codes, starting within 3 business days.
Built for contractors. No spam. No pressure. Just straight answers.
Sample CSI-Based Cost Code List
Example: a commercial GC that self-performs concrete and carpentry and subcontracts everything else. Section numbers and titles follow MasterFormat; the cost types shown are the ones this company would use on each code.
| Cost code | Description | Cost types used | Note |
|---|---|---|---|
| GC-100 | General conditions, time-related staff | L, O | Non-CSI code for PM, superintendent and field office |
| 01 50 00 | Temporary Facilities and Controls | M, E, S | Fencing, temporary power, enclosures |
| 01 74 00 | Cleaning and Waste Management | S, O | Dumpsters and final clean |
| 02 41 00 | Demolition | S | One code; the sub tracks detail |
| 03 10 00 | Concrete Forming and Accessories | L, M, E | Self-performed |
| 03 20 00 | Concrete Reinforcing | S | Furnish-and-install sub |
| 03 30 00 | Cast-in-Place Concrete | L, M, E | Self-performed |
| 06 10 00 | Rough Carpentry | L, M | Self-performed |
| 06 20 00 | Finish Carpentry | L, M | Self-performed |
| 08 11 00 | Metal Doors and Frames | M, L | Supply on M, install on L |
| 09 29 00 | Gypsum Board | S | Drywall sub, framing included |
| 09 91 00 | Painting | S | Painting sub |
| 22 00 00 | Plumbing | S | One code per subcontracted trade |
| 23 00 00 | Heating, Ventilating, and Air Conditioning | S | One code per subcontracted trade |
| 26 00 00 | Electrical | S | Electrical sub, base scope |
| 26 51 00 | Interior Lighting | S | Separate because the contract carries a fixture allowance |
| 31 23 00 | Excavation and Fill | S | Sitework sub |
| MK-010 to MK-040 | Contingency, insurance, bond, fee | O | Markups below the line, never inside a trade code |
Eighteen lines cover the whole job. The self-performed codes carry labor, material and equipment detail because that is where this company’s risk sits. The subcontracted trades get one code each, except where an allowance needs its own line.
How Cost Codes Feed Job Costing
Once the budget is loaded, every cost that hits the job carries a code and a type: subcontracts and purchase orders as commitments, timecards as labor, invoices as material, equipment or other. The cost report then compares budget, committed, actual to date and projected at completion for each line.
Example: code 03 30 00, cast-in-place concrete, self-performed. Every rate is a placeholder.
| Cost type (example) | Budget from estimate | Actual at 60% complete | Projected at completion | Variance |
|---|---|---|---|---|
| L Labor | 420 hrs × $68 = $28,560 | 290 hrs × $68 = $19,720 | $32,867 | $4,307 over |
| M Material | 230 CY × $170 = $39,100 | 141 CY × $170 = $23,970 | $39,950 | $850 over |
| E Equipment | Allowance $4,800 | $3,100 | $5,167 | $367 over |
| Total | $72,460 | $46,790 | $77,983 | $5,523 over |
The projection here is simple: actual to date divided by percent complete (for labor, $19,720 ÷ 0.60). At 60% complete the crew should have used 0.60 × 420 = 252 hours; it used 290, which is 38 hours or about 15% over. Labor accounts for $4,307 of the $5,523 projected overrun, about 78%. Without the cost type split, the report would only say concrete is over budget. With it, the superintendent knows to look at crew size and production, and the estimator knows to check the hours per CY used in the bid.
How Change Orders Flow Through Cost Codes
Price every change on the codes and cost types it will be tracked against, using the same rates as the bid. When the owner approves it, the change revises the budget on those lines, and the cost report measures actual cost against the revised budget.
Example: change order 004 adds six housekeeping pads. Rates are placeholders.
| Code and type (example) | Basis | Amount |
|---|---|---|
| 03 10 00-L | 6 hrs × $68 | $408 |
| 03 10 00-M | Form material | $150 |
| 03 30 00-L | 10 hrs × $68 | $680 |
| 03 30 00-M | 3 CY × $170 | $510 |
| 03 20 00-S | Rebar sub quote | $420 |
| Direct cost | $2,168 | |
| Markup | 15% (example) | $325.20 |
| Change order total | $2,493.20 |
- Track pending changes separately: unapproved work can be coded to the same lines but flagged, so it does not inflate the approved budget.
- Close allowances by change order: report allowance spending from its own code and adjust the prime contract for the difference.
- Keep markup on its own line: fee on changes belongs in a markup code, not inside 03 30 00.
How to Roll Out Cost Codes in Accounting and PM Software
- Set the master list in accountingCost codes are company-level, so build the list once in your accounting or ERP system and treat it as the source of truth.
- Mirror it in project management softwareIn Procore, the default Work Breakdown Structure has a cost code segment and a cost type segment, plus an optional sub job segment. You can use the default codes or import your own with the Procore Imports app. Note that an import can add or edit segment items but cannot delete them.
- Map cost types if you integrateProcore says that with its ERP Integrations tool, cost type items must be assigned to individual cost codes. Check that your accounting categories and Procore’s cost types line up one for one.
- Code your estimate templateEvery line in the template carries a code and cost type from the master list, so the awarded estimate loads straight into the budget. Our guide to what Procore is shows how that budget handoff works there.
- Train the fieldGive foremen a short list of the codes they will actually use on timecards. A long list guarantees miscoding.
- Pilot, then freezeRun one job, fix what confused people, then lock the list. Sage cautions that changing cost codes after transactions are entered is a complex process.
Common Cost Code Mistakes
- A list so long that people guess, which Sage notes leads to data entry errors
- Codes that duplicate cost types, such as separate codes for drywall labor and drywall material
- One list in the estimating software and a different one in accounting
- Mixing 16-division and current MasterFormat numbers across systems
- Markups and contingency buried inside trade codes
- Allowances lumped into base-scope codes
- Renumbering codes mid-year, which breaks comparisons with past jobs
Contingency deserves its own line for another reason: it is a decision, not a cost. Our guide to construction contingency cost covers how much to carry.
Want Every Estimate to Load Straight Into Your Budget?
Get Ninja places a dedicated estimator on your team who prices on your codes, your cost types and your burdened rates, starting within 3 business days.
Built for contractors. No spam. No pressure. Just straight answers.
How a Get Ninja Estimator Builds Estimates on Your Cost Codes
Get Ninja places a dedicated remote construction estimator on your team, trained in US estimating standards and matched to the work you bid, from GC preconstruction to Division 26 electrical and Division 31 earthwork.
- Your code list, every time: estimates built on your cost codes and cost types, so the awarded number loads into the budget without re-keying.
- Your software: Bluebeam, PlanSwift, On-Screen Takeoff, STACK or Procore, with exports that match your accounting categories.
- Change orders priced the same way: each change broken out by code and type at your bid rates.
- Fast start, low risk: Estimators start within 3 business days, with a 3 to 5 day turnaround on a standard estimate, one flat monthly rate, a 30-day money-back guarantee and free replacement for the life of your account.
Frequently Asked Questions
What are construction cost codes?
Construction cost codes are the numbered categories a contractor uses to budget and track job costs, such as 03 30 00 for cast-in-place concrete. Each cost posted to a job, from timecards to supplier invoices and subcontract pay applications, carries a code so actual cost can be compared with the budget.
What is the difference between a cost code and a cost type?
The cost code says what work the cost is for, such as gypsum board or excavation. The cost type says what kind of cost it is: labor, material, equipment, subcontract or other. Sage’s help for Sage 100 Contractor notes that because every job cost gets a cost type, you do not need separate codes for labor and material.
How many cost codes does a contractor need?
Fewer than most people think. Sage’s guidance is that a single-trade subcontractor can usually work with about a dozen codes, a mechanical subcontractor may need around twenty, and a general contractor usually needs one code per subcontracted trade unless it performs that work itself.
Should construction cost codes follow CSI MasterFormat?
Many general contractors do, as Sage’s help notes, because specs, estimates and subcontracts already use MasterFormat. Code at the division and Level 2 section, add cost types, and add your own codes for markups such as fee, bond, insurance and contingency, which MasterFormat does not cover.
How do change orders affect cost codes?
Price each change order line on the same cost code and cost type as the original work. When the change is approved, it revises the budget on those lines, so job cost reports compare actual cost with the revised budget instead of the original estimate.
Can you change cost codes after a job starts?
You can, but it is painful. Sage warns that once transactions are entered with a set of cost codes, changing them is a complex process. Add new codes when you need them, and save structural changes for new jobs.
Related guides
- Sage 100 Contractor Help, About cost codes and divisions. sage.com
- Sage 100 Contractor Help, About cost code numbering for general contractors. sage.com
- Sage 100 Contractor Help, About cost code numbering for subcontractors. sage.com
- Sage 100 Contractor Help, Setting up cost types (and About cost code numbering systems). sage.com
- Procore Support, What are Procore’s default cost codes? support.procore.com
- Procore Support, What are Procore’s default cost types? support.procore.com
- Procore Support, General Contractor Financial Management User Guide: Work Breakdown Structure Setup. support.procore.com
- CSI and CSC, MasterFormat 2011 Numbers and Titles, as published by the NYC Office of Environmental Coordination. nyc.gov
Example quantities are calculated from the stated dimensions. Unit costs, production rates and waste factors are placeholders, not market prices or industry benchmarks. Get Ninja start times are typical, not guaranteed, and pricing is quoted per account.
Olivia Bennet
Olivia Bennet writes Get Ninja's construction estimating guides for US general contractors, home builders and trade contractors: takeoffs, bid preparation, trade pricing and how to staff an estimating backlog. Every article is reviewed by Get Ninja co-founder MJ Suben, who ran a commercial general contracting firm for more than 15 years.