Olivia Bennet writes Get Ninja's construction estimating guides for US general contractors, home builders and trade contractors: takeoffs, bid preparation, trade pricing and how to staff an estimating backlog. Every article is reviewed by Get Ninja co-founder MJ Suben, who ran a commercial general contracting firm for more than 15 years.
MJ Suben is the co-founder of Get Ninja, which places fully trained, dedicated construction estimators with US general contractors, home builders and trade contractors. Before Get Ninja he ran a commercial general contracting firm for more than 15 years, so he reviews every Get Ninja guide against how real bids are priced, leveled and won.
A general conditions estimate prices the contractor’s jobsite costs that belong to no single trade: project staff, the field office, temporary utilities and facilities, cleanup, dumpsters, safety, layout and closeout. Most of it is time-related, so build it per month from the schedule, then add the one-time items. A slipped schedule is a general conditions problem first.
This guide separates general conditions from general requirements and overhead, lists what belongs in each bucket, works a 10-month example month by month, and closes with the 12 items GCs miss most often.
- A general conditions estimate covers jobsite costs that support the whole project. Home-office overhead is a separate markup.
- Split every line into time-related (per month) and fixed (one time). In the example, 86.6% of general conditions cost is time-related.
- Staffing is the largest driver: 61.9% of the example total.
- A two-month slip adds $78,088 to the example, with no change in scope.
- OSHA and EPA rules set some quantities for you: toilets by headcount, fire extinguishers by floor area, and stormwater permit coverage for sites that disturb one acre or more.
Part of our construction estimating guide, which walks through every stage of an estimate from plans to bid day.
General Conditions vs General Requirements vs Overhead: What’s the Difference?
Three terms get mixed up on every bid form. Keep them separate and your estimate gets easier to defend.
| Term | What it means | Where it shows up |
|---|---|---|
| General conditions (contract) | The contract terms that set the rights and duties of owner, contractor and architect. AIA’s standard form is A201–2017, General Conditions of the Contract for Construction. | Contract documents |
| General conditions (cost) | The GC’s jobsite indirect costs: staff, field office, temporary facilities, cleanup, safety and similar items that support all the trades | A line or section in the estimate and schedule of values |
| General requirements (Division 01) | The specification division that states project-wide procedures and temporary work, such as 01 50 00 Temporary Facilities and Controls and 01 70 00 Execution and Closeout Requirements | Project manual; drives many general conditions cost lines |
| Overhead | Home-office costs that are not tied to one job: office rent, accounting, executives, the estimating department | Markup on the bid, not a jobsite line |
Some GCs split jobsite indirects into two lines: “general conditions” for staff and time-related costs, and “general requirements” for Division 01 items such as temporary facilities and cleanup. Either structure works if every item lands in exactly one place. If you organize estimates by MasterFormat, our guide to CSI MasterFormat for estimators shows how Division 01 fits with the trade divisions.
What Goes Into a General Conditions Estimate?
Sort every item by how it is driven. Time-related items scale with months on site. Fixed items happen once. Quantity-driven items scale with area, length or headcount. The Division 01 section numbers below come from CSI MasterFormat and help you match each cost to the spec section that requires it.
| Category | Typical items | Driver | MasterFormat reference |
|---|---|---|---|
| Project staff | Superintendent, project manager, project engineer, assistant super, safety and QC staff | Time (by month and % allocation) | 01 31 00 Project Management and Coordination |
| Field office and storage | Trailer, furniture, storage containers, first aid | Time, plus one-time mobilization | 01 52 13 Field Offices and Sheds; 01 52 16 First Aid Facilities |
| Temporary utilities | Power setup and usage, water, lighting, heat, telecom | Setup is fixed; usage is time | 01 51 00 Temporary Utilities |
| Sanitary facilities | Toilets, handwash stations, drinking water | Time and headcount | 01 52 19 Sanitary Facilities |
| Barriers and enclosures | Temporary fence, barricades, dust barriers, weather enclosures | Quantity (LF, SF) and time | 01 56 00 Temporary Barriers and Enclosures |
| Temporary controls | Erosion and sediment control, stormwater, dust control | Quantity and time | 01 57 00 Temporary Controls |
| Construction aids | Shared hoists, cranes, scaffolding, forklift or telehandler for GC work | Time | 01 54 00 Construction Aids |
| Access and parking | Temporary roads, staging areas, traffic control | Quantity and time | 01 55 00 Vehicular Access and Parking |
| Cleanup and waste | Dumpster pulls, ongoing cleanup labor, final clean | Time and SF | Execution and closeout (01 70 00) |
| Layout and closeout | Mobilization, layout and survey, as-builts, O&M manuals, owner training | Fixed | 01 71 13 Mobilization; 01 71 23 Field Engineering; 01 79 00 Demonstration and Training |
| Signage and identification | Project sign, temporary interior signage | Fixed | 01 58 00 Project Identification |
Permits, testing and utility connection fees belong in the estimate only if the contract assigns them to you. Read Division 00 and Division 01 for who pays, then either carry the cost or exclude it by name.
Rules that set general conditions quantities
- Toilets: OSHA 29 CFR 1926.51 requires 1 toilet for 20 or fewer employees, 1 toilet seat and 1 urinal per 40 workers for 20 or more, and 1 toilet seat and 1 urinal per 50 workers for 200 or more. Price to peak headcount, not average.
- Washing and drinking water: the same standard requires potable drinking water and lavatories with running water, soap and towels or air blowers, with a limited exception for mobile crews.
- Fire extinguishers: OSHA 29 CFR 1926.150 requires a 2A-rated extinguisher for each 3,000 SF of protected building area or major fraction thereof, a maximum 100 ft travel distance, and at least one on each floor.
- Stormwater: EPA states that construction disturbing 1 acre or more, or less than 1 acre within a larger common plan that will disturb 1 acre or more, needs Clean Water Act permit coverage for stormwater discharges. Carry the controls, inspections and maintenance for the whole schedule.
How to Build a General Conditions Estimate Step by Step
- Start from the scheduleBreak the job into months by phase: mobilization, structure, dry-in, finishes, punch and closeout. Staffing and facilities change by phase.
- Build a staffing planShow each role by month with a percentage allocation. A PM at 50% on two jobs is common; a superintendent is usually 100% from mobilization through punch.
- Use burdened ratesSalary plus payroll taxes, insurance, benefits and vehicle. Our guide to calculating construction labor burden walks through the math.
- List facilities from Division 01Go section by section through 01 50 00 and 01 70 00 and price what the spec requires, not what the last job had.
- Quantify the quantity-driven itemsFence by LF, final clean and protection by SF, extinguishers by floor area, toilets by peak headcount.
- Check trade scopes for overlaps and gapsDecide who provides dumpsters, cleanup, temporary power distribution, hoisting and protection. Write it into the bid instructions so subs price it the same way, which also makes bid leveling faster.
- Compare with closed jobsDivide past general conditions cost by months on site. If the new number per month is far off, find out why before you submit.
Worked Example: A Monthly General Conditions Estimate
Example inputs: a two-story, 40,000 SF office building (20,000 SF per floor) on a 2.5-acre site, 10 months from mobilization to closeout, peak crew of 45 workers, and $9,200,000 in direct trade cost. Unit costs are placeholders. Staff costs use the BLS median pay for construction managers, $114,990 a year (May 2025), as a stand-in salary, times a placeholder 1.35 burden factor.
| Time-related item (example) | Basis | Per month |
|---|---|---|
| Superintendent, 100% | $114,990 ÷ 12 × 1.35 | $12,936 |
| Project manager, 50% | Half of the line above | $6,468 |
| Project engineer, 100% | Placeholder burdened cost | $7,500 |
| Safety and QC allocation | Placeholder | $1,000 |
| Field office trailer | Rental | $900 |
| Storage containers | 2 × $200 | $400 |
| Toilets and handwash | 3 units × $180 (2 toilet units for 45 workers, 1 handwash) | $540 |
| Temporary power usage | Placeholder | $1,200 |
| Temporary water | Placeholder | $150 |
| Internet and phones | Placeholder | $250 |
| Dumpsters | 6 pulls × $650 | $3,900 |
| Ongoing cleanup labor | 40 hr × $45 | $1,800 |
| Superintendent vehicle and fuel | Placeholder | $1,100 |
| Safety supplies and signage | Placeholder | $500 |
| Small tools and consumables | Placeholder | $400 |
| Monthly total | Staff $27,904 + facilities $11,140 | $39,044 |
Ten months at $39,044 is $390,440 in time-related cost. The toilet count follows OSHA’s table: 45 workers is “20 or more,” so 1 toilet seat and 1 urinal per 40 workers, rounded up to 2 of each.
| Fixed and quantity-driven item (example) | Basis | Cost |
|---|---|---|
| Mobilize and demobilize trailer and containers | Placeholder | $3,500 |
| Temporary power setup | Placeholder | $8,000 |
| Temporary fence | 1,200 LF × $4.50 | $5,400 |
| SWPPP controls and inspections | 2.5 acres disturbed, so permit coverage applies | $6,500 |
| Project sign | Placeholder | $1,200 |
| Layout and survey | Placeholder | $9,000 |
| Fire extinguishers | 20,000 ÷ 3,000 = 6.67 per floor, so 7 per floor × 2 floors = 14 × $85 | $1,190 |
| Finish protection | 40,000 SF × $0.15 | $6,000 |
| Final clean | 40,000 SF × $0.30 | $12,000 |
| Closeout documents | As-builts, O&M manuals | $2,400 |
| Contractor QC and mock-up allowance | Allowance | $5,000 |
| Fixed total | $60,190 |
Total general conditions: $390,440 + $60,190 = $450,630, or 4.9% of the $9,200,000 example direct cost. That percentage belongs to this example only; it is not a benchmark. Time-related items are 86.6% of the total, and staff alone is 61.9%. Permits and owner testing are excluded here on the assumption that the contract assigns them to the owner.
Is Your General Conditions Line Copied From the Last Job?
Get Ninja places a dedicated GC preconstruction estimator on your team, starting within 3 business days.
Built for contractors. No spam. No pressure. Just straight answers.
The 12 General Conditions Items GCs Miss Most
These are the lines that show up as overruns at closeout. Check every one before you submit.
- Schedule extension. Weather days and late owner decisions add months, and every month repeats the full time-related cost. In the example, two months is $78,088.
- Staff after substantial completion. Punch list, inspections and closeout keep the PM and super on the job after the trades leave.
- Temporary power and water usage. The setup gets priced; the monthly bills often do not.
- Temporary heat and weather protection. Winter enclosures, heaters and fuel for a dry-in or finish phase that lands in cold months.
- Peak dumpster pulls. Drywall and finishes generate far more waste than structure. Price pulls by phase, not one average.
- Cleanup and final clean. Weekly cleanup labor plus a final clean, window cleaning and a second pass before owner move-in.
- Finish protection. Floor, door, frame and elevator protection, and replacing it when it gets damaged.
- Temporary fire protection. Extinguishers by floor area under OSHA 1926.150, plus fire watch if the spec or the jurisdiction requires it.
- Stormwater controls for the whole job. Inspections and maintenance continue until the site is stabilized, not just through grading.
- Hoisting and shared equipment. A forklift or telehandler for GC-scope work and for unloading owner-furnished items.
- Fees the contract assigns to you. Permits, utility connection charges and inspections, if Division 00 or 01 puts them on the contractor.
- Closeout deliverables. As-builts, O&M manuals, attic stock handling and owner training under 01 79 00.
If the schedule looks tight, say so: carry the months you believe, state the duration in your qualifications, and hold a separate contingency for slippage rather than padding every line. Our guide to construction contingency cost covers how much to carry.
How Should You Present General Conditions in a Bid or GMP?
Owners and construction managers ask for general conditions in different forms. Match the format they request and keep your backup ready.
- Lump sum: common on hard-bid work. Keep the monthly build-up in your file so you can price a time extension later.
- Monthly rate: useful when the schedule is uncertain. State what the rate covers and what it excludes.
- Itemized with staffing plan: often requested on negotiated and GMP work. Expect the owner to review rates and allocations.
- Schedule of values: carry general conditions as its own line, billed by month or by percent complete as the contract allows. See how to build a schedule of values from your estimate.
Whichever format you use, code general conditions consistently so you can compare jobs later. A clean set of construction cost codes makes the cost-per-month check in step 7 possible.
How a Dedicated Estimator From Get Ninja Builds Your General Conditions
Get Ninja places a dedicated remote construction estimator on your team, trained in US estimating standards and matched to GC preconstruction, so general conditions are built from the schedule every time.
- Schedule-based build-up: staffing by month and phase, time-related and fixed items separated, quantities from the drawings.
- Division 01 review: every temporary facility, control and closeout requirement in the spec matched to a cost line or a stated exclusion.
- Your rates and history: your burdened rates, vendor pricing and cost per month from your closed jobs.
- Speed and low risk. Estimators start within 3 business days, with a 3 to 5 day turnaround on a standard estimate, one flat monthly rate, a 30-day money-back guarantee and free replacement for the life of your account.
Need Every Bid Built From the Schedule Up?
Add a dedicated preconstruction estimator who works in your software with your rates, starting within 3 business days.
Built for contractors. No spam. No pressure. Just straight answers.
Frequently Asked Questions
What is included in general conditions in construction?
General conditions cover the contractor’s jobsite costs that support the whole project rather than one trade: project staff, the field office and storage, temporary utilities, toilets and drinking water, temporary fence and controls, cleanup and dumpsters, safety, layout and closeout documents.
What is the difference between general conditions and general requirements?
General requirements is Division 01 of the specifications, which states project-wide procedures and temporary work such as 01 50 00 Temporary Facilities and Controls. General conditions, as a cost, is the contractor’s price for jobsite indirect costs, many of which Division 01 requires. As a contract term, general conditions also refers to documents such as AIA A201-2017.
Are general conditions the same as overhead?
No. General conditions are jobsite costs tied to one project, such as the superintendent, trailer and dumpsters. Overhead is home-office cost, such as office rent, accounting and executives, and is usually recovered through markup.
How do you calculate general conditions on a construction project?
Build a monthly cost for time-related items such as staff, trailer, utilities and dumpsters, multiply it by the months on site, then add fixed and quantity-driven items such as mobilization, temporary fence, final clean and closeout. In this article’s example, $39,044 per month for 10 months plus $60,190 of fixed items totals $450,630.
What percentage of construction cost are general conditions?
There is no reliable single percentage, because general conditions depend on schedule length, staffing and what the contract assigns to the contractor. The worked example in this article comes to 4.9% of direct cost, but that is not a benchmark. Build from the schedule and compare cost per month with your own closed jobs.
How many portable toilets are required on a construction site?
OSHA 29 CFR 1926.51 requires 1 toilet for 20 or fewer employees, 1 toilet seat and 1 urinal per 40 workers for 20 or more employees, and 1 toilet seat and 1 urinal per 50 workers for 200 or more. Price to peak headcount.
Related guides
- CSI, MasterFormat 2016 Edition: Numbers and Titles (Division 01 General Requirements), as hosted by the State of Vermont BGS. bgs.vermont.gov
- AIA Contract Documents, A201–2017 General Conditions of the Contract for Construction. aiacontracts.com
- OSHA, 29 CFR 1926.51, Sanitation. osha.gov
- OSHA, 29 CFR 1926.150, Fire Protection. osha.gov
- EPA, Stormwater Discharges from Construction Activities. epa.gov
- U.S. Bureau of Labor Statistics, Occupational Outlook Handbook, Construction Managers. bls.gov
Example quantities are calculated from the stated dimensions. Unit costs, production rates and waste factors are placeholders, not market prices or industry benchmarks. Get Ninja start times are typical, not guaranteed, and pricing is quoted per account.
Olivia Bennet
Olivia Bennet writes Get Ninja's construction estimating guides for US general contractors, home builders and trade contractors: takeoffs, bid preparation, trade pricing and how to staff an estimating backlog. Every article is reviewed by Get Ninja co-founder MJ Suben, who ran a commercial general contracting firm for more than 15 years.