General Conditions Estimate: What GCs Miss and How to Price It

A general conditions estimate prices the contractor’s jobsite costs that belong to no single trade: project staff, the field office, temporary utilities and facilities, cleanup, dumpsters, safety, layout and closeout. Most of it is time-related, so build it per month from the schedule, then add the one-time items. A slipped schedule is a general conditions problem first.

This guide separates general conditions from general requirements and overhead, lists what belongs in each bucket, works a 10-month example month by month, and closes with the 12 items GCs miss most often.

Key Takeaways
  • A general conditions estimate covers jobsite costs that support the whole project. Home-office overhead is a separate markup.
  • Split every line into time-related (per month) and fixed (one time). In the example, 86.6% of general conditions cost is time-related.
  • Staffing is the largest driver: 61.9% of the example total.
  • A two-month slip adds $78,088 to the example, with no change in scope.
  • OSHA and EPA rules set some quantities for you: toilets by headcount, fire extinguishers by floor area, and stormwater permit coverage for sites that disturb one acre or more.

Part of our construction estimating guide, which walks through every stage of an estimate from plans to bid day.

General Conditions vs General Requirements vs Overhead: What’s the Difference?

Three terms get mixed up on every bid form. Keep them separate and your estimate gets easier to defend.

Term What it means Where it shows up
General conditions (contract) The contract terms that set the rights and duties of owner, contractor and architect. AIA’s standard form is A201–2017, General Conditions of the Contract for Construction. Contract documents
General conditions (cost) The GC’s jobsite indirect costs: staff, field office, temporary facilities, cleanup, safety and similar items that support all the trades A line or section in the estimate and schedule of values
General requirements (Division 01) The specification division that states project-wide procedures and temporary work, such as 01 50 00 Temporary Facilities and Controls and 01 70 00 Execution and Closeout Requirements Project manual; drives many general conditions cost lines
Overhead Home-office costs that are not tied to one job: office rent, accounting, executives, the estimating department Markup on the bid, not a jobsite line

Some GCs split jobsite indirects into two lines: “general conditions” for staff and time-related costs, and “general requirements” for Division 01 items such as temporary facilities and cleanup. Either structure works if every item lands in exactly one place. If you organize estimates by MasterFormat, our guide to CSI MasterFormat for estimators shows how Division 01 fits with the trade divisions.

What Goes Into a General Conditions Estimate?

Sort every item by how it is driven. Time-related items scale with months on site. Fixed items happen once. Quantity-driven items scale with area, length or headcount. The Division 01 section numbers below come from CSI MasterFormat and help you match each cost to the spec section that requires it.

3D ninja estimator on a jobsite in front of a site office trailer, with a roll-off dumpster, temporary fencing and a portable toilet.
Trailers, dumpsters, fencing and toilets are classic general conditions.
Category Typical items Driver MasterFormat reference
Project staff Superintendent, project manager, project engineer, assistant super, safety and QC staff Time (by month and % allocation) 01 31 00 Project Management and Coordination
Field office and storage Trailer, furniture, storage containers, first aid Time, plus one-time mobilization 01 52 13 Field Offices and Sheds; 01 52 16 First Aid Facilities
Temporary utilities Power setup and usage, water, lighting, heat, telecom Setup is fixed; usage is time 01 51 00 Temporary Utilities
Sanitary facilities Toilets, handwash stations, drinking water Time and headcount 01 52 19 Sanitary Facilities
Barriers and enclosures Temporary fence, barricades, dust barriers, weather enclosures Quantity (LF, SF) and time 01 56 00 Temporary Barriers and Enclosures
Temporary controls Erosion and sediment control, stormwater, dust control Quantity and time 01 57 00 Temporary Controls
Construction aids Shared hoists, cranes, scaffolding, forklift or telehandler for GC work Time 01 54 00 Construction Aids
Access and parking Temporary roads, staging areas, traffic control Quantity and time 01 55 00 Vehicular Access and Parking
Cleanup and waste Dumpster pulls, ongoing cleanup labor, final clean Time and SF Execution and closeout (01 70 00)
Layout and closeout Mobilization, layout and survey, as-builts, O&M manuals, owner training Fixed 01 71 13 Mobilization; 01 71 23 Field Engineering; 01 79 00 Demonstration and Training
Signage and identification Project sign, temporary interior signage Fixed 01 58 00 Project Identification

Permits, testing and utility connection fees belong in the estimate only if the contract assigns them to you. Read Division 00 and Division 01 for who pays, then either carry the cost or exclude it by name.

Rules that set general conditions quantities

  • Toilets: OSHA 29 CFR 1926.51 requires 1 toilet for 20 or fewer employees, 1 toilet seat and 1 urinal per 40 workers for 20 or more, and 1 toilet seat and 1 urinal per 50 workers for 200 or more. Price to peak headcount, not average.
  • Washing and drinking water: the same standard requires potable drinking water and lavatories with running water, soap and towels or air blowers, with a limited exception for mobile crews.
  • Fire extinguishers: OSHA 29 CFR 1926.150 requires a 2A-rated extinguisher for each 3,000 SF of protected building area or major fraction thereof, a maximum 100 ft travel distance, and at least one on each floor.
  • Stormwater: EPA states that construction disturbing 1 acre or more, or less than 1 acre within a larger common plan that will disturb 1 acre or more, needs Clean Water Act permit coverage for stormwater discharges. Carry the controls, inspections and maintenance for the whole schedule.

How to Build a General Conditions Estimate Step by Step

  1. Start from the scheduleBreak the job into months by phase: mobilization, structure, dry-in, finishes, punch and closeout. Staffing and facilities change by phase.
  2. Build a staffing planShow each role by month with a percentage allocation. A PM at 50% on two jobs is common; a superintendent is usually 100% from mobilization through punch.
  3. Use burdened ratesSalary plus payroll taxes, insurance, benefits and vehicle. Our guide to calculating construction labor burden walks through the math.
  4. List facilities from Division 01Go section by section through 01 50 00 and 01 70 00 and price what the spec requires, not what the last job had.
  5. Quantify the quantity-driven itemsFence by LF, final clean and protection by SF, extinguishers by floor area, toilets by peak headcount.
  6. Check trade scopes for overlaps and gapsDecide who provides dumpsters, cleanup, temporary power distribution, hoisting and protection. Write it into the bid instructions so subs price it the same way, which also makes bid leveling faster.
  7. Compare with closed jobsDivide past general conditions cost by months on site. If the new number per month is far off, find out why before you submit.

Worked Example: A Monthly General Conditions Estimate

Example inputs: a two-story, 40,000 SF office building (20,000 SF per floor) on a 2.5-acre site, 10 months from mobilization to closeout, peak crew of 45 workers, and $9,200,000 in direct trade cost. Unit costs are placeholders. Staff costs use the BLS median pay for construction managers, $114,990 a year (May 2025), as a stand-in salary, times a placeholder 1.35 burden factor.

Time-related item (example) Basis Per month
Superintendent, 100% $114,990 ÷ 12 × 1.35 $12,936
Project manager, 50% Half of the line above $6,468
Project engineer, 100% Placeholder burdened cost $7,500
Safety and QC allocation Placeholder $1,000
Field office trailer Rental $900
Storage containers 2 × $200 $400
Toilets and handwash 3 units × $180 (2 toilet units for 45 workers, 1 handwash) $540
Temporary power usage Placeholder $1,200
Temporary water Placeholder $150
Internet and phones Placeholder $250
Dumpsters 6 pulls × $650 $3,900
Ongoing cleanup labor 40 hr × $45 $1,800
Superintendent vehicle and fuel Placeholder $1,100
Safety supplies and signage Placeholder $500
Small tools and consumables Placeholder $400
Monthly total Staff $27,904 + facilities $11,140 $39,044

Ten months at $39,044 is $390,440 in time-related cost. The toilet count follows OSHA’s table: 45 workers is “20 or more,” so 1 toilet seat and 1 urinal per 40 workers, rounded up to 2 of each.

Fixed and quantity-driven item (example) Basis Cost
Mobilize and demobilize trailer and containers Placeholder $3,500
Temporary power setup Placeholder $8,000
Temporary fence 1,200 LF × $4.50 $5,400
SWPPP controls and inspections 2.5 acres disturbed, so permit coverage applies $6,500
Project sign Placeholder $1,200
Layout and survey Placeholder $9,000
Fire extinguishers 20,000 ÷ 3,000 = 6.67 per floor, so 7 per floor × 2 floors = 14 × $85 $1,190
Finish protection 40,000 SF × $0.15 $6,000
Final clean 40,000 SF × $0.30 $12,000
Closeout documents As-builts, O&M manuals $2,400
Contractor QC and mock-up allowance Allowance $5,000
Fixed total $60,190

Total general conditions: $390,440 + $60,190 = $450,630, or 4.9% of the $9,200,000 example direct cost. That percentage belongs to this example only; it is not a benchmark. Time-related items are 86.6% of the total, and staff alone is 61.9%. Permits and owner testing are excluded here on the assumption that the contract assigns them to the owner.

Example: total general conditions cost by schedule length Vertical bar chart for the worked example. 8 months: $372,542. 10 months as bid: $450,630. 12 months after a two-month slip: $528,718. 14 months: $606,806. Each extra month adds $39,044. Example: general conditions total vs schedule length $39,044 per month time-related + $60,190 fixed $372,542 8 months $450,630 10 months (as bid) $528,718 12 months (slip) $606,806 14 months Bar heights to scale from $0. A two-month slip adds $78,088.
Example only: totals from this article’s worked estimate. Unit costs are placeholders, not market prices.
For General Contractors

Is Your General Conditions Line Copied From the Last Job?

Get Ninja places a dedicated GC preconstruction estimator on your team, starting within 3 business days.

Book a Discovery Call →

Built for contractors. No spam. No pressure. Just straight answers.

The 12 General Conditions Items GCs Miss Most

These are the lines that show up as overruns at closeout. Check every one before you submit.

3D ninja estimator inspecting easy-to-miss jobsite items with a magnifying glass: a fire extinguisher, temporary work lights, a push broom and a first aid kit.
Small site items add up when they are left out of the bid.
  • Schedule extension. Weather days and late owner decisions add months, and every month repeats the full time-related cost. In the example, two months is $78,088.
  • Staff after substantial completion. Punch list, inspections and closeout keep the PM and super on the job after the trades leave.
  • Temporary power and water usage. The setup gets priced; the monthly bills often do not.
  • Temporary heat and weather protection. Winter enclosures, heaters and fuel for a dry-in or finish phase that lands in cold months.
  • Peak dumpster pulls. Drywall and finishes generate far more waste than structure. Price pulls by phase, not one average.
  • Cleanup and final clean. Weekly cleanup labor plus a final clean, window cleaning and a second pass before owner move-in.
  • Finish protection. Floor, door, frame and elevator protection, and replacing it when it gets damaged.
  • Temporary fire protection. Extinguishers by floor area under OSHA 1926.150, plus fire watch if the spec or the jurisdiction requires it.
  • Stormwater controls for the whole job. Inspections and maintenance continue until the site is stabilized, not just through grading.
  • Hoisting and shared equipment. A forklift or telehandler for GC-scope work and for unloading owner-furnished items.
  • Fees the contract assigns to you. Permits, utility connection charges and inspections, if Division 00 or 01 puts them on the contractor.
  • Closeout deliverables. As-builts, O&M manuals, attic stock handling and owner training under 01 79 00.
Price the Schedule Risk Openly

If the schedule looks tight, say so: carry the months you believe, state the duration in your qualifications, and hold a separate contingency for slippage rather than padding every line. Our guide to construction contingency cost covers how much to carry.

How Should You Present General Conditions in a Bid or GMP?

Owners and construction managers ask for general conditions in different forms. Match the format they request and keep your backup ready.

  • Lump sum: common on hard-bid work. Keep the monthly build-up in your file so you can price a time extension later.
  • Monthly rate: useful when the schedule is uncertain. State what the rate covers and what it excludes.
  • Itemized with staffing plan: often requested on negotiated and GMP work. Expect the owner to review rates and allocations.
  • Schedule of values: carry general conditions as its own line, billed by month or by percent complete as the contract allows. See how to build a schedule of values from your estimate.

Whichever format you use, code general conditions consistently so you can compare jobs later. A clean set of construction cost codes makes the cost-per-month check in step 7 possible.

How a Dedicated Estimator From Get Ninja Builds Your General Conditions

Get Ninja places a dedicated remote construction estimator on your team, trained in US estimating standards and matched to GC preconstruction, so general conditions are built from the schedule every time.

  • Schedule-based build-up: staffing by month and phase, time-related and fixed items separated, quantities from the drawings.
  • Division 01 review: every temporary facility, control and closeout requirement in the spec matched to a cost line or a stated exclusion.
  • Your rates and history: your burdened rates, vendor pricing and cost per month from your closed jobs.
  • Speed and low risk. Estimators start within 3 business days, with a 3 to 5 day turnaround on a standard estimate, one flat monthly rate, a 30-day money-back guarantee and free replacement for the life of your account.
GC Preconstruction

Need Every Bid Built From the Schedule Up?

Add a dedicated preconstruction estimator who works in your software with your rates, starting within 3 business days.

Book a Discovery Call →

Built for contractors. No spam. No pressure. Just straight answers.

Frequently Asked Questions

What is included in general conditions in construction?

General conditions cover the contractor’s jobsite costs that support the whole project rather than one trade: project staff, the field office and storage, temporary utilities, toilets and drinking water, temporary fence and controls, cleanup and dumpsters, safety, layout and closeout documents.

What is the difference between general conditions and general requirements?

General requirements is Division 01 of the specifications, which states project-wide procedures and temporary work such as 01 50 00 Temporary Facilities and Controls. General conditions, as a cost, is the contractor’s price for jobsite indirect costs, many of which Division 01 requires. As a contract term, general conditions also refers to documents such as AIA A201-2017.

Are general conditions the same as overhead?

No. General conditions are jobsite costs tied to one project, such as the superintendent, trailer and dumpsters. Overhead is home-office cost, such as office rent, accounting and executives, and is usually recovered through markup.

How do you calculate general conditions on a construction project?

Build a monthly cost for time-related items such as staff, trailer, utilities and dumpsters, multiply it by the months on site, then add fixed and quantity-driven items such as mobilization, temporary fence, final clean and closeout. In this article’s example, $39,044 per month for 10 months plus $60,190 of fixed items totals $450,630.

What percentage of construction cost are general conditions?

There is no reliable single percentage, because general conditions depend on schedule length, staffing and what the contract assigns to the contractor. The worked example in this article comes to 4.9% of direct cost, but that is not a benchmark. Build from the schedule and compare cost per month with your own closed jobs.

How many portable toilets are required on a construction site?

OSHA 29 CFR 1926.51 requires 1 toilet for 20 or fewer employees, 1 toilet seat and 1 urinal per 40 workers for 20 or more employees, and 1 toilet seat and 1 urinal per 50 workers for 200 or more. Price to peak headcount.

Sources
  1. CSI, MasterFormat 2016 Edition: Numbers and Titles (Division 01 General Requirements), as hosted by the State of Vermont BGS. bgs.vermont.gov
  2. AIA Contract Documents, A201–2017 General Conditions of the Contract for Construction. aiacontracts.com
  3. OSHA, 29 CFR 1926.51, Sanitation. osha.gov
  4. OSHA, 29 CFR 1926.150, Fire Protection. osha.gov
  5. EPA, Stormwater Discharges from Construction Activities. epa.gov
  6. U.S. Bureau of Labor Statistics, Occupational Outlook Handbook, Construction Managers. bls.gov

Example quantities are calculated from the stated dimensions. Unit costs, production rates and waste factors are placeholders, not market prices or industry benchmarks. Get Ninja start times are typical, not guaranteed, and pricing is quoted per account.