Procore Bid Management: Send ITBs, Track Coverage, Level Bids

Procore bid management is the workflow inside Procore’s project-level Bidding tool for sending invitations to bid (ITBs), collecting subcontractor pricing on standardized bid forms, tracking who intends to bid, leveling the bids side by side and converting the winner into a subcontract or purchase order. It takes bidding out of spreadsheets and email inboxes.

This guide walks through the setup in the order you will use it, from bid package to award, based on Procore’s own support documentation. It then covers how to raise subcontractor coverage and where the tool stops.

Key Takeaways
  • The work happens in five places: the bid package, bid forms, the bidder list, the Bid Leveling tab and the Commitments tool.
  • Bid forms, bid leveling and per-bid-form status tracking exist only in the Bid Management Enhanced Experience, and Procore says a project moved to it cannot be switched back.
  • Coverage lives in the Bidders tab: Intent to Bid and Submission Status, filterable by trade.
  • Leveling adjustments override the leveled total without changing the bidder’s original submission, and you can award either version.
  • Updating bid documents does not notify invited bidders on its own. Send a correspondence every time.

Part of our construction estimating software guide, which compares the tools contractors use for takeoff, pricing and bid tracking.

What Is Procore Bid Management?

Procore describes its Bidding tool as a way to solicit bids for projects while providing a central location for managing and viewing the status of all bids. Subcontractors download the bid package and submit bids back into Procore, so the bid list, the documents and the numbers stay in one project record instead of scattered email threads. If you are new to the platform, start with our overview of what Procore is and who it is for.

3D ninja estimator at a laptop showing bid package folders, with a rolled drawing set, a spec binder and a stack of bid envelopes.
Bid packages, ITBs and bids live in one project workspace.

There are two versions. Procore’s FAQ says the Bid Management Enhanced Experience adds bid forms, bid leveling and Procore Construction Network integration, and tracks bid status, notes and activity separately for each bid form rather than per company. A company can accept the Electrical bid form and decline the HVAC one, and both statuses are recorded. Procore also notes that once a project is updated to the new experience, it cannot be switched back. Everything below assumes the enhanced experience.

Stage Where it lives in Procore What you set up
Bid package Bidding tool, Create Bid Package Name, due date, RFI deadline, instructions, documents, privacy
Bid forms Bid package, Bid Forms Base bid and alternate line items, by cost code
Bidder list and ITBs Bid form bidders, Invite Companies from your Directory, invitation emails, reminders
Questions and addenda RFI Deadline, correspondence, Files tab Pre-bid answers and updated documents
Coverage Bidders tab Intent to Bid, Submission Status, Last Activity
Leveling Bid form, Bid Leveling tab Adjustments, notes, private line items, alternates
Award Award Bidder, then Commitments Subcontract or purchase order with its schedule of values

How to Set Up Procore Bid Management, Step by Step

  1. Check permissionsCreating a bid package requires Admin permissions on the project’s Bidding tool, and the Primary Bidding Contact needs Admin too. Procore’s permissions notes say Read Only and Standard users can only view leveled bids, and converting an award also requires Admin on the Commitments tool.
  2. Create the bid packageClick Create Bid Package and fill in Name, Number, Status (Open while bidding, Closed once awarded), Primary Bidding Contact and Bid Submission Notifications. Set the Bid Due Date (or check To be determined), RFI Deadline, Anticipated Award Date, Pre-Bid Meeting Date and Site Walkthrough Date. Project Description and Bidding Instructions appear in the invitation.
  3. Choose the settingsBid Reminder Emails start a set number of days before the due date and go out daily at 11:30 AM UTC. Flexible Bid Due Date accepts late submissions. Offline Bids blocks submission in Procore. Blind Bidding hides all bids until the due date, with an optional Manager who can reveal them early. You can also require a Non-Disclosure Agreement, or turn on Public Discovery to list the package on the Procore Construction Network.
  4. Attach the documentsAdd files from Drawings, Documents or Specifications. Procore recommends a dedicated Documents folder for bid files and warns that packages with more than 100,000 files can slow the application.
  5. Build one bid form per tradeCreate forms New, From CSV or From Template (Beta). Add sections, then Cost Code or Plain Text line items to the Base Bid and Alternates. Each line takes a Response Field Type: Amount, Unit/Quantity or Include/Exclude (base bid only). For a lump-sum bid, Procore says to set every line to Include/Exclude so bidders enter one total.
  6. Add bidders and send ITBsAdd companies from your Directory to each bid form, then use Invite for one company or the banner that shows how many invitations are still unsent. Invited bidders can declare their intent to bid from the invitation email.
  7. Handle questions and addendaQuestions come in before the RFI Deadline, and you answer them through the Bidding tool. When documents change, edit the package’s Files tab and click Update, then send a correspondence. Procore says invited bidders keep the link to the original documents until you do.

Number your bid forms and line items the way you number your estimate. Our guide to CSI MasterFormat for estimators shows how to keep packages, cost codes and the estimate on one structure.

For General Contractors

Spending Bid Week Chasing Subs Instead of Pricing the Job?

Get Ninja places a dedicated estimator on your team who can run your bid packages in Procore, starting within 3 business days.

Book a Discovery Call →

Built for contractors. No spam. No pressure. Just straight answers.

How to Track Bid Coverage in Procore

Coverage is the count of real bids you can expect on each trade. In Procore it lives in the bid package’s Bidders tab, which shows Company Name, Recipient List, Last Activity, Bid Invitation Last Sent, Intent to Bid, Submission Status, Bid Amount, Cost Codes, Trades and Notes. Intent to Bid shows whether a company plans to bid, and Submission Status shows whether it has submitted. Procore notes you can filter, search and group the list, which is how you check coverage trade by trade.

3D ninja estimator pinning status dots on a bid coverage board with rows of trade icons, tracking which trades have bids.
Check coverage trade by trade well before bid day.

Review it on a fixed schedule, not just on bid day. In the example below, plumbing, HVAC and roofing are below the GC’s target two days out, so those are the trades to phone today.

Example bid coverage by bid formExample grouped bar chart of bidders invited, bidders intending to bid and bids submitted for six bid forms: concrete 8, 4, 3; electrical 10, 5, 4; plumbing 7, 3, 2; HVAC 6, 2, 1; drywall 9, 5, 4; roofing 5, 3, 2. Plumbing, HVAC and roofing are highlighted in orange as below an example target of three submitted bids. Example: bid coverage by bid form, two days before bid Invited Intend to bid Submitted Example target: 3 bids 0 2 4 6 8 10 12 8 4 3 Concrete 10 5 4 Electrical 7 3 2 Plumbing 6 2 1 HVAC 9 5 4 Drywall 5 3 2 Roofing Orange bars: submitted bids below the example target
Example only: illustrative bidder counts for six bid forms. The three-bid target is an example, not an industry standard.

Tips to raise subcontractor coverage

  • Invite early and wide: send ITBs as soon as the documents are ready, and add more companies than you need on thin trades.
  • Split packages by trade: separate bid forms let a sub bid only its scope, and Procore tracks each form’s status separately.
  • Use Public Discovery: listing the package on the Procore Construction Network lets new trade partners find it.
  • Turn on reminder emails: automatic daily reminders start a set number of days before the due date.
  • Call the silent ones: filter for companies with no intent to bid and phone them, starting with your best past performers.
  • Make bidding easy: short bid forms, clear scope, the right documents and fast answers to questions.
  • Protect the relationship: treat every number confidentially. Subs remember which GCs shop their bids.

How to Level Bids in Procore

Procore’s Bid Leveling lines up submissions side by side so you can compare them line by line and spot scope gaps and outliers. Open the bid package, click the bid form, open the Bid Leveling tab and choose Leveled Bids. How you adjust depends on each line’s response type:

  • Amount: enter a number that overrides the calculated total without changing the company’s original submission. This is where your plug for missing scope goes.
  • Include/Exclude: include or exclude the line in the calculation while keeping the original data.
  • Unit & Quantity: change quantity, unit cost or unit type, and the total recalculates.
  • Notes and history: add a note explaining each adjustment, color-code lines and check View Activity. Edited cells show a triangle in the corner.
  • Private lines and alternates: add private line items for scope no bidder priced, and toggle alternates on or off.

Leveling only works on bid packages created after October 2023 with response types configured, and only after a bid form exists and bids are in. Here is why it matters:

Electrical bid form (example) Submitted Scope gap Plug Leveled total
Bidder A $412,000 Excludes fire alarm +$31,000 $443,000
Bidder B $438,500 None $0 $438,500
Bidder C $425,750 Excludes temporary power +$9,500 $435,250

The lowest submitted number becomes the highest leveled one. Bidder C is low once scope is equal, at $435,250, which is $23,250 above Bidder A’s headline price. The plugs are your own estimate of the missing scope, which is why leveling still needs an estimator. Our bid leveling guide covers the method line by line.

How to Award a Bid and Create the Commitment

The Commitments tool must be enabled to convert winning bids. From the Leveled Bids view, click the ellipsis next to the company and choose Convert to Subcontract or Convert to Purchase Order. Procore then asks which version to use: the Leveled Bid (with your adjustments, private line items and alternates) or the Submitted Bid. Click Award and Convert, and Procore opens the new contract’s General tab. Review the Schedule of Values tab, then use Email Contract to send it.

  • Soft award: mark the bid awarded without creating a contract yet.
  • Check the schedule of values: Procore says the appropriate information is copied over automatically but does not list every field, so confirm cost codes and amounts. Our guide to the schedule of values explains what a clean one looks like.
  • ERP cost types: with an ERP integration, set the cost type on the contract. For QuickBooks Desktop, Procore says subcontracts should always use Other (O).

Limits of Procore Bid Management

  • Moving a project to the enhanced experience is permanent.
  • Bid leveling works only on packages created after October 2023 with response types set; sections need packages created from January 2024.
  • Creating bid forms from templates is still in Beta.
  • Bid packages are snapshots. Changed documents don’t reach invited bidders until you update the package and send a correspondence.
  • It manages bidding, not takeoff. Your plugs, budget and leveling decisions still come from an estimate.
  • Procore doesn’t publish prices. As of October 2026 its pricing page asks buyers to request a custom quote, so check what your plan includes before you build a bid workflow around it.

The bid workflow above follows the same habits we describe in construction estimating best practices: scope sheets, coverage checks and a second look before award.

How a Get Ninja Estimator Runs Procore Bidding for You

Get Ninja places a dedicated remote construction estimator on your team who can run this whole workflow inside your own Procore account, with the permissions you set. You keep the bidder relationships and the award decisions; your estimator does the setup, the chasing and the leveling.

  • Packages and bid forms built by trade and cost code, with your documents, instructions and alternates.
  • Coverage management: ITBs, reminders and follow-up calls until every trade has the bids you want.
  • Leveling with real plugs from takeoffs in your software, such as Bluebeam, PlanSwift, On-Screen Takeoff or STACK.
  • Award-ready summaries so your PM can convert the winner into a commitment.
  • Speed and low risk. Estimators start within 3 business days, with a 3 to 5 day turnaround on a standard estimate, one flat monthly rate, a 30-day money-back guarantee and free replacement for the life of your account.
Procore Users

Want Full Coverage and Leveled Bids on Every Package?

Get Ninja places a dedicated estimator in your Procore account to run ITBs, coverage and leveling, starting within 3 business days.

Book a Discovery Call →

Built for contractors. No spam. No pressure. Just straight answers.

Frequently Asked Questions

What is Procore bid management?

It is the workflow in Procore’s project-level Bidding tool for creating bid packages, inviting subcontractors, collecting bids on bid forms, tracking intent to bid and submissions, leveling bids and converting the winner into a subcontract or purchase order.

Can you hide bid amounts until the due date in Procore?

Yes. Turn on Blind Bidding in the bid package settings to hide all bids until the bid due date passes. You can name a Manager who can reveal the bids earlier if needed.

How do you level bids in Procore?

Open the bid form, go to the Bid Leveling tab and choose Leveled Bids. Adjust amounts, include or exclude lines, change units and quantities, add notes and private line items, and toggle alternates. Adjustments override the leveled total without changing the bidder’s original submission.

How do you turn a Procore bid into a subcontract?

With the Commitments tool enabled, click the ellipsis next to the winning company and choose Convert to Subcontract or Convert to Purchase Order. Pick the leveled or submitted bid, click Award and Convert, then review the schedule of values and email the contract.

What is the difference between the legacy and enhanced bidding experience?

The enhanced experience adds bid forms, bid leveling and Procore Construction Network integration, and it tracks bid status, notes and activity for each bid form instead of each company. Procore says a project moved to the new experience cannot be switched back.

How much does Procore bid management cost?

Procore does not list prices on its website. Its pricing page directs buyers to request a custom quote, so pricing depends on the products and contract you negotiate.

Sources
  1. Procore Support, Bidding (project-level user guide and permissions). support.procore.com
  2. Procore Support, What is the difference between the old and new bid management experience in the Bidding tool? support.procore.com
  3. Procore Support, Create a Bid Package with Bid Management Enhanced Experience. support.procore.com
  4. Procore Support, Create a Bid Form. support.procore.com
  5. Procore Support, View a Bid Package. support.procore.com
  6. Procore Support, Update Bid Documents. support.procore.com
  7. Procore Support, Level Bids for a Bid Form. v2.support.procore.com
  8. Procore Support, Award a Bid and Convert it to a Subcontract or Purchase Order. v2.support.procore.com

Example quantities are calculated from the stated dimensions. Unit costs, production rates and waste factors are placeholders, not market prices or industry benchmarks. Get Ninja start times are typical, not guaranteed, and pricing is quoted per account. Procore is a trademark of Procore Technologies, Inc. Feature details reflect Procore’s support documentation as of October 2026.